Monday, October 13, 2008

Brick work for inside walls


Brick work for partition walls and to raise walls to reach slope roof bottom are being done.Picture shows sit out view at present

Saturday, October 11, 2008

Slope roof after concreting


Picture shows slope roof after concreting

Slope roof concreting


Picture shows slope roof getting ready for concrete

Flat roof concrete


Picture shows flat roof after concreting using ready mix machine

Flat roof concreting


Rear side of the roof is concreted as Flat roof with portions visible from front side to be concreted later as slope roof.Picture shows flat roof ready for concrete using ready mix machine concrete

Brick work


Picture shows brick work in progress and doors and windows being fixed in place

Kattila Veypu(First Door being fixed)


Door window frames for the house was ready before we started building brick work.Usual Kattila Veypu ceremoney was conducted where the First Door fixing is done with Pooja and distribution of sweets.Picture shows door being fixed in place